E101
SEEDING AND MULCHING^^

THE FOLLOWING QUANTITIES ARE PROVIDED TO PROMOTE
GROWTH AND CARE OF PERMANENT SEEDED AREAS:

659, SOIL ANALYSIS TEST            ____ EACH
659, TOPSOIL                       ____ CY
659, SEEDING AND MULCHING          ____ SY
659, REPAIR SEEDING AND MULCHING   ____ SY
659, INTER-SEEDING                 ____ SY
659, COMMERCIAL FERTILIZER         ____ TON
659, LIME                          ____ ACRES
659, WATER                         ____ MGAL
659, MOWING                        ____ MSF

SEEDING AND MULCHING SHALL BE APPLIED TO ALL AREAS OF
EXPOSED SOIL BETWEEN THE RIGHT-OF-WAY LINES, AND WITHIN 
THE CONSTRUCTION LIMITS FOR AREAS OUTSIDE THE RIGHT-
OF-WAY LINES COVERED BY WORK AGREEMENT OR SLOPE
EASEMENT. QUANTITY CALCULATIONS FOR SEEDING AND 
MULCHING ARE BASED ON THESE LIMITS.~~


Designer Note:
Use the above quantities on all projects that require grading work. The
following is a basic guideline for estimating quantities for the above items. These
quantities may be omitted from the note if they are itemized elsewhere in the plan.
Calculations for all items should be shown in the plans.

659, Soil Analysis Test (EACH)

    Soil Analysis Tests are used to field adjust the rate of Lime based on soil conditions.

    A.   Soil Analysis Test is not specified.

         1.   The standard rate for Lime will be used without adjustment.

    B.   Soil Analysis Test is specified. If specified, minimum of two tests.

         1.   If no Topsoil to be placed - One test per 10 Acres (one test per 48400 Sq. Yd.)
              of permanent seeded area and sodded area.

         2.   If placing Topsoil - One test per 10000 Cu. Yds. of Topsoil.

659, Topsoil (CY)

    111 Cu. Yds. per 1000 Sq. Yd. of permanent seeded area. Topsoil is optional. However,
    it is recommended, especially for projects involving A4 silty materials, granular
    embankment or granular materials due to severe erosion problems.

659, Seeding and Mulching (SY)

    This quantity is usually calculated by the end width method using the cross sections.
    On short projects, seeding quantities may be determined by other methods. For example,
    the area for seeding may be estimated by calculating an area per Plan and Profile sheet
    determined by multiplying an average width (based on construction limits or
    right-of-way lines) by the distance on each sheet, and then deducting for paved surface
    areas. A deduction should be taken for 660 and 670 items.

659, Repair Seeding and Mulching (SY)

    5% of the permanent seeding and mulching area.

659, Inter-seeding (SY)

    5% of the permanent seeding and mulching area.

659, Commercial Fertilizer (TON)

    30 pounds per 1000 Sq. Ft. (one Ton per 7410 Sq. Yd.) of permanent seeded area. This
    rate includes 20 pounds per 1000 Sq. Ft. for the first application and 10 pounds per
    1000 Sq. Ft. for the second application. If Inter-seeding is provided, use an
    additional 20 pounds per 1000 Sq. Ft. of commercial fertilizer for the Inter-seeding
    area.

659, Lime (ACRE)

    Apply over permanent seeded area.

659, Water (MGAL)

    Two applications each at 300 Gallons per 1000 Sq. Ft. (0.0027 M Gallons per Sq. Yd.)
    of permanent seeded area. The above rate is for a single application. If Inter-seeding
    is provided, use an additional 300 Gallons per 1000 Sq. Ft. of water for the
    Inter-seeded area.

659, Mowing (MSF)

    25% of the permanent seeded area for projects expected to last more than one
    construction season.~~


E102
SODDING^^

THE FOLLOWING QUANTITIES ARE PROVIDED TO PROMOTE
GROWTH AND CARE OF PERMANENT SODDED AREAS.

659, SOIL ANALYSIS TEST            ____ EACH
659, TOPSOIL                       ____ CY
659, COMMERCIAL FERTILIZER         ____ TON
659, LIME                          ____ ACRE
659, WATER                         ____ MGAL
660, SODDING, UNSTAKED, STAKED, REINFORCED   ____ SY~~

Designer Note:
Provide the above quantities on all projects that have pay item(s) for permanent
sodding. The following is a basic guideline for estimating quantities for the above items.
These quantities may be omitted from the note if they are itemized elsewhere in the plan.
Calculations for all items should be shown in the plans.

659, Soil Analysis Test (EACH)

    Soil Analysis Tests are used to field adjust the rate of Lime based on soil conditions.

    C.   Soil Analysis Test is not specified.

         1.   The standard rate for Lime will be used without adjustment.

    D.   Soil Analysis Test is specified. If specified, minimum of two tests.

         1.   If no Topsoil to be placed - One test per 10 Acres (one test per 48400 Sq. Yd.)
              of permanent sodded area.

         2.   If placing Topsoil - One test per 10000 Cu. Yds. of Topsoil.

659, Topsoil (CY)

    111 Cu. Yds. per 1000 Sq. Yd. of permanent sodded area. Topsoil is optional. However,
    it is recommended, especially for projects involving A4 silty materials, granular
    embankment or granular materials due to severe erosion problems.

659, Commercial Fertilizer (TON)

    30 pounds per 1000 Sq. Ft. (one Ton per 7410 Sq. Yd.) of permanent sodded area. This
    rate includes 20 pounds per 1000 Sq. Ft. for the first application and 10 pounds per
    1000 Sq. Ft. for the second application.

659, Lime (ACRE)

    Apply over permanent sodded area.

659, Water (MGAL)

    1 application every 7 days for an additional 2 months beyond the requirements of
    660.09. The rate shall be 300 gallons per 1000 Sq. Ft. (0.0027 M. Gallons per Sq. Yd.)
    of permanent sodded area.

660, Sodding (SY)

    This is the actual number of Sq. Yds. of permanent sodded area.~~